Liulang Cave Underground Hydropower Station
Liulang Cave Underground Hydropower Station: The Liulang Cave Underground Hydropower Station is China’s first underground reservoir-based power station and was once included in school textbooks. Surveying began in 1954, construction started in February 1958, and both 1.25-megawatt generating units were completed and put into operation by February 1960. The station has an installed capacity of 2.5 megawatts and an average annual output of 150 million kWh. The total capacity of the underground reservoir is 82,400 cubic meters, with measured minimum flow of 24 m/s and maximum of 74 m/s. The station adopts a diversion-type development, and the tailwater is directly discharged into the Nanpan River after power generation. Since its commissioning, the Liulang Cave power station has been in operation for 46 years, generating a total of 6 billion kWh.